| CRESTON & DISTRICT COMMUNITY COMPLEX FACILITY ENHANCEMENT PROJECT WHAT'S HAPPENING RIGHT NOW:Recycle, Recycle, Recycle!
Recycling asphalt, concrete, and fill is high on Hedlund’s priority list as they excavate layers of material in preparation for the new curling slab.
95 % of the standing walls have been completed by NW Construction (out of
In this picture you can see the previous layer of asphalt previous to the addition being added in the late 80’s. We are currently assessing footing depth location to further proceed with excavation. WHAT YOU CAN EXPECT TO SEE HAPPEN WITHIN THE NEXT TWO WEEKS:
CURLING RINK DEMOLITION
ARENA CHANGEROOMS (beginning the plumbing)
This project is funded by The Canada-British | ||||||||||||||||||||||||||||||||||||||||||||